Sector – Healthcare
Discipline – Mechanical & Electrical
Budget - £170,000
Scope of works - Volmech were contracted to full M&E services for two MDT rooms within Imperial college NHS trust, this work consisted of AC design and Installation, Vent Design and installation and a full power and lighting installation including new supplies from the hospital’s substations, these rooms are critical for Multiple discipline meetings for critical care patients in ICU. The works were installed and completed within an 8 week program.